In this guide
Before lifting
Check the lintel designation against the drawings. Prepare the specified mortar, lifting equipment, temporary supports and measuring tools. Set out both bearing areas and compare their length with the structural detail.
Position the lintel
Prepare the supporting masonry and lay the specified mortar bed. Lift the element into its marked position. Check that it is level and that both ends have full bearing. Fill joints and keep temporary supports in place for the period specified by the installation plan.
Adapt the detail to the masonry
Brick, expanded-clay block and aerated concrete walls can use different bearing details. Check material-specific requirements before installation. Wider openings, unusual wall geometry and concentrated floor loads may require a designed beam or cast-in-place detail.
Inspect before covering
Check the product mark and batch certificate, bearing at each end, level, filled joints and any specified supports or reinforcement. Keep the product documents with the record for concealed works.
Frequently asked questions
What fills the gap between a lintel and masonry?
Fill the joint with the mortar specified for the detail, without voids. The source uses M100 cement–sand mortar as its example.
Should the lintel be supported while the mortar sets?
Keep the temporary supports shown on the installation drawings until the assembly is ready to take load.
Can I use thin-bed adhesive under a lintel in aerated concrete?
Check the designed bearing detail. The source describes a cement–sand mortar bed for these precast units.
When can masonry continue above the lintel?
The required mortar strength and curing conditions govern when the lintel can be loaded. Follow the project installation plan.
What if the span exceeds the range?
Ask the structural designer to specify a beam or a cast-in-place solution for that opening.